what are the dates that land can be cleared for pipeline construction in Ohio?  I believe it is April 1 to Sept 30?

Views: 392

Reply to This

Replies to This Discussion

Trees can be cut between September 1st and April 1st.

http://minerals.ohiodnr.gov/portals/minerals/pdf/coal/procedure%20d...

Bats give birth to one baby called a "pup"   sometime in the months of June and July.    So it appears the regulations give an extra month on both sides of that range.

well I just talked to the pipeline people and it is 10-1 start and finish by 3-31 for clearing of trees.

RSS

Local Groups





Blog Posts

Shale Gas News – October 21, 2017

Posted by Thomas J Shepstone on October 23, 2017 at 9:10am 0 Comments

The Shale Gas News, heard every Saturday at 10 AM on 94.3 FM, 1510 AM and Sundays on YesFM, talked about seismic testing, wastewater recycling, microturbines and much more last week.

The Shale Gas News has grown…

Continue

Events

October 2017
SMTWTFS
1234567
891011121314
15161718192021
22232425262728
293031
       

© 2017   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service