Permit on engineers report applied by Enervest on August 19 in clay township. Acreage is 153.2 acres. Looks like they will be drilling a well soon.

Views: 27796

Replies to This Discussion

keep up the great reporting! Need to see the rig show up very soon.

Yes the pad is built!

do you know what the road is being built for on county road ten before you get up to the nettle well . in the bottoms. thanks buz

No not sure. But I see they have a night guard there now.and they brought the power lines in today. Must be go time.
I saw that road there is a stack of pipes could be a pipe line?

we will probably find out soon enough, ill have to take a walk down there this weekend, thanks buz

the rig is up for the nettle well

Got a pic tena?

i do have one but dont know how to post it

Attachments:

well i guess i do know how to do it  but i hope someone who lives closer to the well can get a better one.

I will go up tomorrow and get a few pics!

I talked to the guard tonight .You can really see it at night its all lit up.He said it will take a month or so to drill it.

RSS

© 2024   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service