Can anyone give any updates on what is happening in Greene County, PA?  Specifically Richhill and Jackson Townships?  I'm getting a lot of calls/cards in the mail so I am assuming something is happening...

Views: 350

Reply to This

Replies to This Discussion

So far in 2019...

Richhill: 18 wells went into production

Jackson: no wells went into production

In total 43 wells went into production in Greene Co. as a whole. It is taking 170 days to go from permit to drilling and 638 days to go from permit to drilling. 

Data from Marcellusgas.org

In the state of PA, only 37 rigs are active. 6 of those are in Greene Co.

Data from Baker Hughes

Good information there, thank you! I have property over in Center Township. Looks like I'm getting close to payout finally, but I have one question about what you stated here "taking 170 days to go from permit to drilling and 638 days to go from permit to drilling." I'm not sure what you're saying. Is this just a typo, or are you talking about different types of wells? Thanks!

Sorry - typo 

638 days to go from Permit to Producing.

You can look at some of the info on this site without having a membership

https://www.marcellusgas.org/history/history.php

That's what I thought. Thanks again!