What is the going rate for pipeline easements from Bluegrass Pipeline? They want to pay by the acre with a 50 foot perminant easement. I always thought you got payed by the inch diameter per foot? What is the going rate per acre? They only want 2 acres across my property.

Views: 2642

Reply to This

Replies to This Discussion

BEWARE OF THE LANDMAN THEY ARE ALL OUT FOR THE COMPANY AND NOT FOR THE LANDOWNER .....THE COMPANY PAYS THEM .....THE LOWER THEY GET THE ROW FOR THE MORE THEY GET PAYED .....THEY TRY MAKING U BELEIVE THEYARE UR BUDDYY BUT REALLY THEY ARE JUST CARPET BAGGERS ,,HERE TODAY AND GONE TMORROW ........LOOKING FOR THEIR NEXT SUCKER .......HAVE A GOOD ATTORNEY LOOK OVER ANY CONTRACTS U ARE OFFERED ......DONT SIGN ANYTHING WITHOUT LEGAL ADVICE .......ONCE U SIGN UR LOCKED IN FOR EVER ..........LOTS A THING NEED TO BE COVERED THAT THEY TEND TO SKIP OVER ....LIKE WHO IS PAYING THE PROPERTY TAXES ON THOSE ACRES FOR THE NEXT EVER .........TIMBER LOSE ........WATCH THAT THE ROW IS ONLY FOR ONE PIPELINE AND ANY FUTURE PIPELINES ARE A NEW CONTRACT AND PAYMENT .....IF MORE THEN ONE PIPELINE EACH PIPELINE NEEDS TO BE PAYED FOR .........THEY LIKE TO BUNDLE ON ONE CONTRACT ...ANY STRUCTURE ABOVE GROUND LIKE METER STATIONS OR VALVES NEED TO BE PAYED FOR SEPERATE FROM THE PIPELINE .......THAT PIPELINE IS GOING TO MAKE THEM MILLIONS AND THEY NEED TO PAY LANDOWNERS FAIRLY ..THE FOMULA FOR PAYMENT SHOULD BE PIPE DIAMETER AT SO MUCH PER INCH TIMES LINEAR FOOT OF ROW  FOR EXAMPLE 3.00 X24INCHES TIMES 1280 FEET IMHO THEN THE FUTURE TAXES ON THE LAND ..THEN TIMBER LOSE....THEN ANY ABOVE GROUND STRUCTURES  TEMPORARY EASEMENT NEEDS TO BE PAYED FOR TOO

Mike, You have some good input on GMS. But I'm having difficulty reading your comments written in all capital letters. Would you please help out the my older eyes and use sentence-style capitalization? Thank You.

Sorry I get gone and forget to turn off the cap lock 

It is a 20" line and they are paying 15,000.00 per acre for the permanent easement. Sounds a little low to me!

IT IS LOW AND U NEED TO GET AN ATTORNEY  I KNOW OF A ROW THE LAND OWNER GOT 100 BUCKS PER FOOT IN WETZEL COUNTY NEAR PROCTOR

Because this is an interstate pipeline, do they have the right of eminent domain? 

Once FERC issues the certificate of approval, they first have to acquire a threshold percentage of ROW parcels, then the eminent domain enters into the equation. From my understanding, this pipeline is for export purposes out of an Louisiana facility, not for public necessity. However, they indicate to supply industries along the projected route. This would be the trump card to establish public necessity in order to implement eminent domain. This is a time sensitive project as eminent domain court cases would tie it up too long in court. Landowners have the provision of The First Amendment for trial in court. I would assume they would use land condemnation in lieu, if Just Compensation could not be agreed on. Just my opinion.

  