I'd try to make friends with some other people in the unit so that you can keep updated.
As for timelines, it takes about six months to get a permit, from what I hear. Then it takes two months to put in road, well pad, frac pond. Then actual drilling takes three weeks but often they have to wait a couple of months to get a rig on site as they are all booked solid and any delay at a previous site delays everything down the line.
Fracking and completion can take another month or two, along with the same availability issues. Then you need a pipeline to get the gas to market, maybe compressors, dehydrators, or other processing equipment to prepare gas for market. And most leases allow for 90 days or more after production begins before royalties are paid.
Like bill h said, plan on a year or more before royalties begin to roll in.
© 2024 Created by Keith Mauck (Site Publisher). Powered by
h2 | h2 | h2 |
---|---|---|
AboutWhat makes this site so great? Well, I think it's the fact that, quite frankly, we all have a lot at stake in this thing they call shale. But beyond that, this site is made up of individuals who have worked hard for that little yard we call home. Or, that farm on which blood, sweat and tears have fallen. [ Read More ] |
Links |
Copyright © 2017 GoMarcellusShale.com