what are the dates that land can be cleared for pipeline construction in Ohio?  I believe it is April 1 to Sept 30?

Views: 392

Reply to This

Replies to This Discussion

Trees can be cut between September 1st and April 1st.

http://minerals.ohiodnr.gov/portals/minerals/pdf/coal/procedure%20d...

Bats give birth to one baby called a "pup"   sometime in the months of June and July.    So it appears the regulations give an extra month on both sides of that range.

well I just talked to the pipeline people and it is 10-1 start and finish by 3-31 for clearing of trees.

RSS

Local Groups





Blog Posts

Plastic, Brought to You by Natural Gas

Posted by Thomas J Shepstone on November 21, 2017 at 1:11pm 0 Comments

Most people use plastic products every day, but what they may not know is that natural gas plays a huge role in its manufacturing.

There is now another reason natural gas is so important in our everyday lives,…

Continue

Events

November 2017
SMTWTFS
1234
567891011
12131415161718
19202122232425
2627282930
       

© 2017   Created by Keith Mauck (Site Publisher).   Powered by

Badges  |  Report an Issue  |  Terms of Service