Any more info on the Hall pad  off of Rt 151  past Bethel Church?

Views: 8278

Replies to This Discussion

still working on it rig is still supposed to be here mid april

Pics taken 2/20/2014. Cutting access road to pad site...

Attachments:

Thank you very much

everything is coming together pretty nice .Lots of dirt to move filling in gulleys for the pad .Now almost ready to finally be done dealing with the pipeline company .Wanting to put in valve station .

 

Pics taken 2/27/2014. Access road to pad site...

Attachments:

thanks

The pad and road are pretty much complete

thanks for the update

the pad is done

Attachments:

Thanks ,keep us informed

moving in part by part

Attachments: