I was wondering when negotiating if asking for damages on additional pipe to be laid at a later date is common? thanks for any help
Tags:
Some people have, I'm assuming this wouldn't be hard to get on a transmission line. Its just depends on how much tax you want to pay.
thanks for the responding i appreciate it
Jason - When we negotiated our pipeline agreement, they have to pay original amount again for any future lines. They also have to honor original agreement on all levels for each additional line, including payment, if they need them. All around us negotiated same.
620 members
505 members
396 members
160 members
167 members
© 2026 Created by Keith Mauck (Site Publisher).
Powered by
What makes this site so great? Well, I think it's the fact that, quite frankly, we all have a lot at stake in this thing they call shale. But beyond that, this site is made up of individuals who have worked hard for that little yard we call home. Or, that farm on which blood, sweat and tears have fallen. [ Read More ]