Still drilling away on 702. Moved rig to new hole on 702 not new pad.
Does that mean they have drilled one lateral?
and are starting a second?
Moved the rig again on Sat. If they are averaging 18 days a hole like some of the companies they could have this unit completed before the end of the year.
They have pulled a small rig in on the 703 pad and have started drilling to get ready for the big rig when they finish up on the 702 pad. The 703 pad has 8 laterals with closer spacing. Looks like an interesting 2014 shaping up.
Hi Sam,
Thanks for the update.
So what is the current status of 702?
How many holes have they put down?
Have they drilled laterals?
Where is 703?
They moved the rig again on Sunday. I would think they are starting on the 6th hole. The 703 pad is on the next hill over to the north.
Thanks.
Do you have a map showing 703's location?
You can find it on the ODNR website.
http://oilandgas.ohiodnr.gov/well-information/oil-gas-well-locator
They took the rig down on Wedn. I think they may be done drilling on the 702 site. I hope to see it go up on the 703 site this week.
Thanks. I really appreciate the update.
Will they be fracking soon?
How long will that process last?
When do you predict they will be in production?
Fracking going on on the 702 site. nothing happening on the 703 site its been 6 weeks since they finished up drilling on 702 so this doesn't look good. Everyone else is ramping up the drilling and HG goes on vacation.
© 2024 Created by Keith Mauck (Site Publisher). Powered by
h2 | h2 | h2 |
---|---|---|
AboutWhat makes this site so great? Well, I think it's the fact that, quite frankly, we all have a lot at stake in this thing they call shale. But beyond that, this site is made up of individuals who have worked hard for that little yard we call home. Or, that farm on which blood, sweat and tears have fallen. [ Read More ] |
Links |
Copyright © 2017 GoMarcellusShale.com