Anyone know what the rotary rig was drilling for on the ROW on Fredericktown Road on Monday and Tuesday?

Views: 1608

Reply to This

Replies to This Discussion

NORTH BEAVER PIPELINE PHASE 2 ESGP-2
Client: UTICA GAS SVCS LLC
Authorization type: Erosion and Sediment Control GP-2
Application type: New
Authorization is for: SITE
Date received: 04/19/2013
Status: Issued on 9/25/2013

Hi Larry

Not sure exactly where you are talking about ? Deemston on Ridgewood dr? 

only says South Beaver Twp.   Nothing more specific on the site.

http://www.ahs.dep.pa.gov/eFACTSWeb/searchResults_singleSite.aspx?S...

Ok, so this pipeline is only going to South Beaver TWP? 

NOT Southern Beaver County, Correct?

From the minutes of Beaver County Planning Commission

South Beaver Twp – Utica Gas Services. LLC (UGS) (2) 1) Permit for North Beaver Pipeline, Phase 2 (installing a 12 inch natural gas pipeline, 2 six inch well connect lines & associated access roads.)  2) Permit for Rolling Acres Gathering Line and Maga Well Connect Pipeline (installing a 10 inch natural gas pipeline and 6 inch national gas pipeline). 

North Beaver Pipeline Project – Appalachia Midstream Services, LLC
Act 14 notice: installation of approx. 4.2 miles of 10” natural gas gathering pipeline
from 3 natural gas wells to a compressor station along an existing transmission pipeline

That is all the information I can find at the moment.

Thanks for the info larry. I'll see if I can get anymore info from the twp folks.

Ok thanks for your help Larry.