Tags:
More than you probably want to know about natural gas pipelines. From the Argonne National Laboratory:
http://corridoreis.anl.gov/documents/docs/technical/APT_61034_EVS_T...
Kathi,
I just had a 24" line put through my place, in the initial Row I gave them 50 feet. When they got ready to install they marked 100 feet. After a lot of discussion and rereading the addendums I did they remarked to 75 feet, so more discussion and rereading contract and addendum. Finally remarked to 50 feet. The pipe line install crew didnt like it but they managed.
I just didnt want a freeway running though my wooded areas. So the short of it is they can manage in 50 foot space
The 50 feet row was a permanent row for 1 pipeline only. They paid single payment by foot across land, 30 is what I got but think i could of held out for 50 but maybe not with the 50 foot. Specified double ditch method for stock piling top soil. Got paid for double timber value and had logs piled for my use after clearing. I eliminated the temporary easements on either side.
Have rumours of people getting annual payments but havent seen it happen for pipelines, Compessor stations yes but not pipelines in our area
© 2024 Created by Keith Mauck (Site Publisher). Powered by
h2 | h2 | h2 |
---|---|---|
AboutWhat makes this site so great? Well, I think it's the fact that, quite frankly, we all have a lot at stake in this thing they call shale. But beyond that, this site is made up of individuals who have worked hard for that little yard we call home. Or, that farm on which blood, sweat and tears have fallen. [ Read More ] |
Links |
Copyright © 2017 GoMarcellusShale.com